1.1.................... moves to amend H.F. No. 7, the first engrossment, as follows:
1.2Page 6, after line 27, insert:
1.3"(f) The implementation of all standard obligations of an electric utility under this section
1.4is automatically suspended for a period of two years following:
1.5(1) an interruption of electric service to more than 15 percent of the electric utility's
1.6Minnesota customers that lasts more than 24 hours; or
1.7(2) two interruptions of electric service within a 12-month period to more than 15 percent
1.8of the electric utility's Minnesota customers that each last more than 12 hours.
1.9This paragraph does not apply to any interruption of electrical service that is caused by a
1.10natural disaster."